Finland orders halt to preparatory work at two planned Google data centre sites

Finland's Supervisory Agency (LVV) has ordered work suspended at planned Google data centre sites in Muhos and Kajaani over forest clearance of more than 300 hectares. Google says it "fell short of our own high standards".

3 outlets · 2L · 1C · 0R First reported Account updated
Image: BBC News
Image: The Guardian
Image: Al Jazeera

1 / 3

The story, neutrally told

Mixed · 2Finland's Supervisory Agency (LVV) has ordered a halt to preparatory work at two planned Google data centre sites, in Muhos and Kajaani, amid concerns over the clearance of more than 300 hectares of forest. Mixed · 2LVV said work at one site was carried out without a mandatory environmental impact assessment, and it ordered measures that would significantly alter the environment to be suspended immediately, and no later than 23 October 2026. Mixed · 2LVV's head of environment, Tommi Muilu, said the work included removing trees and topsoil, building site roads and storage areas, and altering ditches.

Mixed · 2Tuike Finland, the company behind Google's data centre projects, must explain and set out how it will proceed by 14 October, and LVV said it could begin "enforcement proceedings" if the company does not comply. Mixed · 2Hanna Halmeenpaa, chair of the Finnish Association for Nature Conservation, told AFP that "nature sites which should be preserved" had been felled; the group had earlier called for work to stop while environmental requirements were examined. Centre · 1Google told the BBC it had "fallen short of our own high standards in this instance" and would follow the agency's guidance, while saying it had "acted in good faith under the Forestry Act", carried out nature surveys and put in place measures to protect high-value areas.

Left · 1Google spokesman Sondre Ronander told AFP the company would "study the LVV's findings and follow their guidance" and was advancing landscaping and biodiversity plans, including tree planting across 130 hectares at Muhos. Mixed · 2The sites are part of Google's €13bn investment in Finland over 2027 and 2028, announced last month and described as its largest single investment in Europe, covering data centres in Kajaani, Muhos and Vaala and its existing Hamina facility. Centre · 1The package includes a 22-year power purchase agreement with Fortum for up to half the output of the Loviisa nuclear plant, which Fortum says would support its operation until 2050; Google says construction would support more than 37,000 jobs.

Left · 1Al Jazeera places the order in a wider debate: opposition parties last month called for a national permit system to prevent power shortages and soaring energy prices, with Centre Party leader Antti Kaikkonen saying Finland must ensure enough electricity and transmission capacity, and the Social Democrats voicing concern over power demand.

Every sentence links to the reporting it rests on. The pill in front of each says where its sources sit: Left, Centre or Right when one side supplies at least half of them, Mixed when they are evenly split. The number is how many outlets it cites.

Left2 outlets

Framing
Frames the order within growing political and consumer scrutiny of AI data centres and their energy demands.
Emphasis
Opposition calls for a national permit system, power shortage and energy price worries, and Google's AI ambitions.
Leaves out or plays down
Does not carry Google's 'good faith under the Forestry Act' defence or its jobs and economic contribution figures.
Charged language
“United States tech giant”“soaring energy prices”
For example
“AI builders are now facing greater scrutiny from consumers and politicians.” — Al Jazeera

Centre1 outlet

Framing
A regulatory-enforcement story led by the order and the forest clearance, with Google's response given prominence.
Emphasis
Google's statement to the BBC, the good-faith claim under the Forestry Act, the €13bn investment, jobs and economic benefit.
Leaves out or plays down
Does not mention the opposition parties' calls for a national permit system or power-supply concerns.
Charged language
“fallen short of our own high standards”
For example
“Google said it had "fallen short of our own high standards in this instance" and would follow the agency's guidance.” — BBC News

Right0 outlets

No right outlet in our sources has covered this story yet.